Jiangsu Council Vocational College Infrastructure Project Change and Visa Management Measures
Author:  Release time: 2023-05-18   Views:500

Chapter 1  Total  

The first article isFurther specificationSchoolProject in the basic construction projectChange and visa managementBehaviorMake sure to ensure the construction of the project efficiently and orderly,and effective control of the project cost,According to relevant national and provincial and municipal regulations,In conjunction with the actual situation of the school, formulate this method.

Two Project change and the cumulative amount of engineering visa shall not exceed the contract price10%. Engineering changes, visa cumulative cumulative contract amount10%, needScripturesDisciplinary inspection, auditFinance, logisticsJoint meeting discussed by leaders of relevant departments, reportsCourtyardLong office meetingResearch and review。The labor fee that has been clearly stipulated in the contract、Material cost increase or decrease does not count on project changes。

Chapter 2  Project change

Article 3 Project change in this method,refers to the following situations in the construction process of construction projects:

(1) Change of design drawings,Original design drawings cannot meet the requirements of actual construction;

(2) Change the function and construction plan of the construction plan due to the use unit;

(3) Important materials and equipment technical parameters、Function changes;

4On -site construction conditions are not consistent with technical materials such as survey reports;

(5) Because of the law、Regulations、The change caused by the adjustment of the rules and regulations;

(6) Other changes.

Article 4 The change of the project of the basic construction project should follow the scientific nature、feasibility、Economics、feasibility、Approve first、After changing、The principle of re -construction; approval sky bet login in strict accordance with the prescribed procedures and approval authority,Engineering changes that have not been implemented in accordance with the prescribed procedures,The main body of the change is responsible for。

Article 5 Project changes can be used by the construction unit according to the actual situation、Design Unit、Use Department、Logistics Management OfficeProposal,According to the requirements, the change department fills in the project contact form,Change after approval by project change。When there is a repair、Ins emergency、Emergency Project、endangering personal safety and force majeure and other reasons,The person in charge of the construction unit project can verbally notify the construction unit、The supervision unit implements changes and implemented it on this matter7Complete the approval procedures within working days,Reserved and provided on -site video information。

Chapter 3  Approval of project changes

Article 6  The construction of the project involves normal acceptance and does not involve changes in the cost of engineering cost,Drafting project change contact form from the use department on -site,The person in charge of the Logistics Management Office signed an opinion,and apply for approval according to the school approval authority。

Article 7  Change of the plan proposed by the unit、Change of use、Material change or other large changes,Approval permissions are divided as follows:

aSingle change costEstimation1Within 10,000 yuan(including110,000 yuan)Project change,The person in charge of the proposal department, audit、Logistics、Supervision、Research and demonstration of construction units,From the proposed department representative drafting project change contact form,The person in charge of the Logistics Management Office is approved for implementation。

2Single change costEstimation1More than 10,000 yuan2less than 10,000 yuan(Includes210,000 yuanProject changeThe person in charge of the proposal department, audit、Logistics、Supervision、Research and demonstration of construction units,From the proposed department representative drafting project change contact form,The person in charge of the logistics management officeAfter approval,ScripturesLeaders in charge of schoolAfter signing the opinionImplement.

(3) Single item change costEstimation210,000 yuanaboveProject change, shouldDisciplinary inspection, auditFinance, logisticsand other relatedThe person in charge attended the expert demonstration meeting and formed a meeting minutes,Related investigation or research if necessary,From the proposed department representative drafting project change contact form (attached expert demonstration meeting minutes)Signed opinions in charge of leaders,Implementing the approval of the president of the president。

4All changing visa items shouldFill in the "Application Form for Engineering Change of Jiangsu Finance and Accounting Vocational College" (see the attached table for format),Organized after approval。

Article 8 The design changes involved in the project change In principle, the original design unit of the project is responsible for perfection、Modifying Design。If the change content exceeds the qualification range of the original design unit,After the original design unit agrees with the original design unit,It can be borne by bidding or entrusted other units with corresponding qualifications。

Article 9 The content of the design change is implemented by the original contract construction unit,When the original unit does not have the qualifications of the content of the design engineering content,You must select other construction units through the corresponding school program to complete the design and change the construction content。

Article 10 Responsibility for project changes:

(1) Due to survey、Design、Construction、The negligence of the relevant units such as supervision caused the project to change and cause economic loss,Logistics managementDivided by the relevant provisions of the contract shall be required to bear financial compensation liability;

(2) The approved project changes shall not make secondary changes in principle; no unit shall not be approved by the intention to resolve the change project,If you find it,will be held accountable for relevant units and personnel;

(3) Construction sky bet games online units shall be carried out strictly in accordance with the approved change documents,If the corresponding construction period and economic loss are caused if the construction is not under construction,The construction unit bears liability and compensates for losses

Article 11 After the project is changed、Send hair。Project change documents shall be numbered according to the project continuous、Unified format、Clear handwriting、Do not have wrong words。

Chapter 4  Engineering visa

Article 12 Engineering visa refers to the agreement in accordance with the contracting contract,The signing proof process made by the representatives of the Chengfa contract involved in the contract price during the construction process,Generally occur during construction、The work content that cannot be reflected on the construction and completion charts (such as coverage、Hidden、Receiving、Demolition、Scrap、Wo Gong、stagnation, etc.)。

Engineering visa and engineering changes have a clear scope of handling,Any change that can be reflected in the completion drawings,It should not be confirmed by on -site visa procedures。

Article 13 The content of the engineering visa should follow the authenticity、Accuracy、Principles of Reason and Time,The content of the engineering visa should be clear、Implementation of pre -approval、After -after acceptance,Take care of efficiency and efficiency,Engineering visa should be conducive to improving project functions、Improve the quality of the project and promote the implementation of the project。

Article 14 Engineering visa shall be implemented with a project contact form、Design change file、Use unit contact form requirements, etc.,The principle of engineering visa again。

Article 15 The type of engineering visa is as follows:

(1) Visa for changes in construction conditions,refers to the venue during the construction process、Environmental construction conditions and underground、Wall、Ceiling and other unpredictable Sky Bet app and zero boundary conditions change,Construction organization caused by、Design solution、Technical measures, etc. of temporary modification;

(II) Error correction and perfecting visa,refers to the requirements of the use unit、Contract defects、Defense、Design changes or construction diagram errors caused by rework or technical processing measures caused by the construction party or contractor's economic loss;

(3) Engineering construction visa,It is mainly due to the main materials during the implementation process、Development of the equipment caused by the equipment entry and retirement and the owner's reasons、Passing or shortening the visa of the construction period;

(4) The original construction unit refused to do it、omissions、Projects that need to be entrusted with third -party construction;

(5) Visa caused by the omissions and errors due to the list of engineering quantities。

Article 16 Project Visa Content Normality:

Engineering visa form must be stated that the reasons for change,Clear the type of visa、Determine visa fee。Conditional change Visa must clarify the materials that cannot be reflected on the facts and drawings that occur in the project、quantity、Location and size; Error correction and improvement of the class visa must be clear about the content of the corresponding measures、Engineering quantity,and attach a contract or corrected contract、drawings; engineering -oriented visa should be marked with manual、Mechanical classroom、Workload, etc.。All visas should be accurate engineering amount、Reasonable expenses、Clear handwriting、Writing specification、The cause of the visa is clear、Measurement unit is consistent with the quota or list。

For on -site visas that cannot be calculated after the hidden project and afterwards,,Construction unit、Project leader、Supervision unit、Tracking the audit unit personnel must witness according to the icon and on -site completion before the hidden (or demolition)、Checking、Measurement,Do a good video record sky bet login as a visa basis,Do a good job of signing records for the amount of engineering volume,You must only measure according to the icons provided by the contractor after no incident。

Chapter 5   Approval of engineering visa

Article 17 Engineering visa cost amount should be accurate,Engineering visa shall be submitted by the construction unit,Construction unit Fill in the on -site engineering visa form,On -site engineering visa single format,The construction unit notified by the supervision unit、Construction unit、Tracking audit unit to the scene to witness。Economic Supervision Unit、Tracking Audit Audit,NewsLogistics Management OfficeThe approval process is as follows:

aSingle itemamount1Within 10,000 yuan (including110,000 yuan)Engineering visa,It is proposed that the department representative fills in the project visa approval form,Report the Logistics Management Office for review、The person in charge for approval;

2Single itemamount110,000 yuan-210,000 yuanInsideIncludes210,000 yuan)Engineering visaFrom the proposed department representative, audit、Logistics、Supervision、Research and demonstration of construction units,It is proposed that the department representative fills in the project visa approval form,The person in charge of the logistics management officeAfter approval,ScripturesLeaders in charge of schoolAfter signing the opinionImplement.

(3) Single itemamount210,000 yuanaboveProjectVisa, shouldDisciplinary inspection, auditFinance, logisticsand other relatedThe person in charge attended the expert demonstration meeting and formed a meeting minutes,Related investigation or research if necessary,It is proposed that the department representatives fill out the project visa approval form (the meeting of the experts demonstration of the meeting)Signed opinions in charge of leaders,Implementing the approval of the president of the president。

4All engineering visa projects shouldFill in the "Approval Form for Engineering Vocational Vocational College of Jiangsu Finance and Accounting Vocational College" (see the format in the format),Organized after approval。

Article 18 Engineering visa liability:

The person in charge of the project on the project should analyze the cause of the visa regularly,Continuous improvement of construction site management level。Error correction visa caused by the reasons of the construction party,Evaluation should be performed on a regular basis; the error correction visa Sky Bet caused by the design unit or the total bag unit,Should be designed、A method of dealing with the agreed treatment in the main package contract,Cause serious losses,It should be held accountable for its economic responsibility。The on -site visa approval procedure without changing or construction without the program,Not a basis for project settlement,The consequences caused by this shall be borne by the construction unit。

Chapter 6  Attach  

No. 119strip When the project is completed and settled,,The competent department of engineering is based on the "Application Form for Engineering Change of Jiangsu Council Vocational College", "Jiangsu Council Vocational College Engineering Visa Approval Form", and related subjects for relevant discussions、Settlement of information such as changing scheme,No approval in accordance with the requirements of these measures、Improper procedures、Change and visa beyond permissions,Not as a basis for settlement。

Article 20 For units and individuals who violate these measures,It will depend on its plot weight,Carefully deal with the discipline according to law。

Article 21 These measures will be tried from the date of announcement.IfThe relevant terms in these Measures and the current law of the countryRegulationsand regulationsDisapmenttimeIt is implemented in accordance with national laws, regulations and regulations.

Article 22 This method is fromLogistics managementis responsible for explanation.


             